FANGDA GROUP NHI: INNOVATION MANAGEMENT AND SERVICE FIRST

Published:2021-03-25

In the manufacturing and on-site installation of the two drum-type mixer of Shiheng Special Steel Group Co., Ltd, NHI provided the all-star intimate service to ensure the high-quality delivery of the project, and once again won the trust and full recognition of the steel enterprise customers.

Since the successful implementation of the mixed system reform last year, NHI has comprehensively introduced the mature and advanced system, mechanism and management mode of Fangda Group, and continuously carried out reform and innovation in sales, design, procurement, production and other aspects. Relying on the strong steel industry layout and resource advantages of Fangda Group, NHI has strengthened the development of major equipment and market development for steel enterprises. It has not only passed the evaluation of Baosteel suppliers with high marks, but also carried out equipment manufacturing for Fangda Iron and Steel and other outstanding enterprises in the steel industry.

Mixed Reform Boost Development, Energize Enterprises in an All-round Way

After the implementation of the mixed reform, NHI has gradually established a modern corporate governance model of "owner supervision and operator responsibility". In accordance with the principle of centralized, lean and efficient management, the operation structure was reconstructed, and part of the management departments were "canceled, merged and transferred", so as to realize the unified management of production, supply, marketing, technology and finance, and make the enterprise operation and production organization more standardized. At the same time, by implanting the refined management concept of Liaoning Fangda Group, standardize the enterprise operation with the system, guide the cadres and employees with the market-oriented principle, formulate and introduce the assessment and incentive policy of "work until you receive, work more and get more", which has completely broken the " communing pot ".

With the full help and support of Fangda Group and its brother’s enterprise, NHI quickly recovered market orders and quickly realized full load production operation. The frontline workers have jobs, and their income is not only guaranteed, but also significantly increased, the workers are satisfactory and motivate, an enterprise on the verge of bankruptcy in mixed reform coruscate a new vitality. After completion of the reorganization and implementation of judicial reform from April 30th 2019, the new order reached 1.857 billion yuan in the same year, up 43.28% year-on-year. Restructuring income plus production and operation achieve a profit of 560 million yuan. In the first quarter of 2020 alone, the severe challenges caused by COVID-19 epidemic were overcome, and the new orders reached 1.03 billion yuan, up year-on-year increase of 275%. In a short period of one year, after the mixed-use reform, Fangda Group NHI has won many good news, and behind a brilliant report card, it also confirms the full release of the reform effect and the significant improvement of market competitiveness.

Since the mixed reform, a series of reform measures have been taken to meet the needs of the public, from salary increase to welfare increase, or to the big red envelope for on-job employees and retired employees. The benefits brought by the mixed reform let the majority of cadres and employees see the hope of the future development of the enterprise, strengthen the confidence of development and the beautiful yearning for the future life, and stimulate the passion of starting a business again.

Blows Honest Bugle, Improve Quality, Catch Delivery

After the mixed reform, NHI kept its promise to ensure delivery on time as the main work to reshape the market image. The company held a special product contract project kick-off meeting, and implemented each item. Backward project completion schedule and time node based on product delivery date. Blow the horn of "trustworthy project", quickly set off to catch production, guarantee period, reduce the cost of the crucial.

Since the drum-type mixer project of Shiheng Special Steel was officially started, in order to ensure the smooth completion of the construction period of the two cylinder mixers of Shiheng Special Steel, according to the sequence of site installation, NHI made a scientific and reasonable assembly completion plan, divided all parts into assembly nodes and delivered them in order to prepare for site installation. During the assembly of the mixer, the Production Safety Department of Materials Equipment Branch fully played the role of connecting the preceding with the following. On the one hand, it carried out on-site monitoring of the assembly, and on the other hand, it communicated and coordinated with various professionals such as process, technology and inspection, which effectively ensured the timeliness of the complete projects and the effective utilization of resources. Lin Haifeng, Liu Pan, Wang Shiheng, Lv Haibo and other key members of the assembly workshop of the branch plant were not afraid of hardship and fatigue. They innovated assembly methods, solved technical problems, and promoted the implementation of projects with high quality. At the same time, a group of assembly staff gave up holidays and rest time to work overtime for assembly, and successfully completed the delivery of the project at the fastest speed.

Carefully Serve Users On Site, Establish Beautiful Brand

“No matter how much effort we pay, how much bitterness we taste, we all feel it is worth it.” At the beginning of April last year, Wang Yufeng and Tu Jiancheng from the Third Assembly Workshop of the Mining Building Materials Equipment Branch were sent to the installation site of the 265 square meters sintering line mixer of Shiheng Special Steel. They overcame the high temperature and rainy environment and served the site with care based on customer needs, which established a good reputation for NHI and won the trust of users.

The weather in Shiheng Special Steel installation site was hot, sometimes as high as 32 degrees. But Wang Yufeng and Tu Jiancheng still chose to stick to the scene and organize the installation of equipment. Due to multiple and disorder construction on site, in order to unload the arriving equipment on time without delay, they mobilized everyone to clean the site in time to ensure the working conditions. In order to complete the delivery, they started work in advance every day, and often gave up the rest time at noon to continue to study the follow-up construction plan. In the evening, they insisted on finishing the day's work and thinking about the task of the next day in advance.

In the process of installation, for the workpiece with inclination requirements, the user required slurry method. In order to meet the needs of users, they led the team members to use their spare time in the evening to learn construction methods. Finally, all kinds of on-site problems were overcome, 72 slurry piles were completed in two days, and the parameters such as height, level and slope were guaranteed, which were recognized by the users. Recently, the installation site needs to adjust the rollers. In the face of sudden rain and cooling, they covered the level with their only umbrella and ensured the alignment of the idler despite the fact that they were drenched all over.

Steel has always been the dominant industry that Fangda Group focused on. As the core enterprise of heavy machinery under Fangda Group, NHI is also advancing to the goal of being the best steel equipment manufacturing service provider in China with the concept of customer-oriented and excellence and practical actions.